UUU 1 - Complete rental agreement providing premises, stalls, arcades and markets.
Duration : 14 Working Days
Month
Total Application
Tahun 2017
Total Application
Comply KPI
( 14 Working Days )
Total Application
Not Comply KPI
( More than 14 Working Days)
Client Charter
Achievement Status
%
Achievement
%
Not Achieve
January 50 50 0 100% 0%
February 15 15 0 100% 0%
March 20 20 0 100% 0%
April 12 11 1 92% 8%
May 21 21 0 100% 0%
June 14 14 0 100% 0%
July 16 14 2 88% 13%
August 15 15 0 100% 0%
September 14 14 0 100% 0%
October 18 17 1 94% 6%
November 5 5 0 100% 0%
December          
TOTAL 200 196 4 98% 2%

 

UUU 2 - Filed the case after the approval of the prosecution.
Duration : 14 Working days
Month
Total Application
Tahun 2017
Total Application
Comply KPI
( 14 Working Days )
Total Application
Not Comply KPI
( More than 14 Working Days)
Client Charter
Achievement Status
%
Achievement
%
Not Achieve
January 0 0 0 0% 0%
February 0 0 0 0% 0%
March 1 1 0 100% 0%
April 0 0 0 0% 0%
May 0 0 0 0% 0%
June 0 0 0 0% 0%
July 0 0 0 0% 0%
August 0 0 0 0% 0%
September 1 1 0 0% 0%
October 0 0 0 0% 0%
November 0 0 0 0% 0%
December          
TOTAL 2 2 0 100% 0%

 

UUU 3 - Revised draft MPJBT agreements with third parties.
Duration : 60 Working days
Month
Total Application
Tahun 2017
Total Application
Comply KPI
( 60 Working Days )
Total Application
Not Comply KPI
( More than 60 Working Days)
Client Charter
Achievement Status
%
Achievement
%
Not Achieve
January 7 7 0 100% 0%
February 9 9 0 100% 0%
March 10 10 0 100% 0%
April 10 10 0 100% 0%
May 15 15 0 100% 0%
June 18 18 0 100% 0%
July 6 6 0 100% 0%
August 13 13 0 100% 0%
September 11 11 0 100% 0%
October 10 10 0 100% 0%
November 10 10 0 100% 0%
December          
TOTAL 130 130 0 100% 0%